The Mystery of the Old MOC Funds

When Mayor Ed Gainey announced an end to the Mon-Oakland Connector (MOC) shuttle road at the February 17 Greater Hazelwood community meeting, residents of affected communities applauded. They immediately requested basic improvements like safe street crossings, sidewalks and facilities for after-school programs. Officials offered no specific plans for redistributing MOC funds, but early reports focused on building a biking and walking trail that follows the same MOC route.

Five months after the MOC’s formal demise, as the bike/pedestrian trail project moves forward piece by piece, details on leftover MOC funds remain murky. 

When we contacted Emily Bourne, communications specialist for Pittsburgh’s Department of Mobility and Infrastructure (DOMI), she said in a June 10 email that $6.7 million remains in the budget for the MOC, which she referred to as the Four Mile Run project.

“All of the funds are still in Four Mile Run named capital accounts,” Ms. Bourne wrote. “Any movement would require council action unless spent on something connected to the Four Mile Run project.”  

However, Pittsburgh’s 2021 capital budget reported the project had $7.7 million in “unexpended/unencumbered prior year funds.” This figure aligns with the one provided to us by DOMI’s chief engineer Eric Setzler in late 2021. He said in a phone call, “I am seeing about $8 million [of City funds].” 

Peering inside the magic bag

Some of the $1 million difference between the 2021 and 2022 figures can be explained by money that was diverted from the MOC budget.

In December 2020, City Council passed a budget amendment introduced by Councilman Corey O’Connor that moved $4.15 million out of the MOC. Those funds were divided among affordable housing programs, support for small businesses throughout Pittsburgh, and infrastructure improvements in Hazelwood. This should have left around $3.85 million in MOC funds.

But Ms. Bourne, when asked to confirm this, emailed that the diverted money was “not actual funds.”

“Had the budget been passed as introduced they would have been, but they were moved before the budget was adopted,” Ms. Bourne wrote. “There could have been other budget moves but nothing with actual obligated funds.”  

“The only transfer was from December 2021 when Council moved $575,000 from Mon-Oakland ‘Four Mile Run’ to Street Resurfacing,” she added.

Indeed, Councilman O’Connor did introduce a budget amendment to remove $575,000 from the MOC funds. Of those, $550,000 went to new lights for Bud Hammer Field in Greenfield and $25,000 went to repair steps around Burgwin Field in Hazelwood.

It is unclear how the Bud Hammer Field lights and Burgwin Field steps are related to street resurfacing, and where the $4.15 million in the 2020 budget amendment originated if not from MOC funds. Also unexplained is the $4 million shown in the 2021 capital budget as going back into the MOC for 2022. 

Asked to comment during a June 10 phone conversation, Councilman O’Connor said, “People at DOMI are not very intelligent. Whoever you were talking to does not know what they are talking about. We always make amendments before a budget is passed. Only the final draft of the budget matters.”

The 2022 capital budget contains no mention of the MOC. Councilman O’Connor explained this by saying the project “would not have to be listed in the capital budget if the funds have already been allocated,” and no new funding was being requested. 

About 7% of the $8 million in the fund last December is unaccounted for by our reckoning. This could be a calculation error due to rounding, or it might actually be missing. But the funds still exist and are being spent on lights and steps, at the very least.

Table showing known expenses or allocations and remaining balance calculated, compared against DOMI's reported MOC budget as of June 2022
Table showing known expenses or allocations and remaining balance calculated, compared against DOMI’s reported MOC budget as of June 2022

When will our money fund our solutions?

One fact has become plain over the past five months: The project and its funding will continue—minus Almono Partners’ proposed shuttles and the MOC name.

This slow-walked continuation of the project formerly known as the MOC raises concerns among members of MOC-affected communities. Residents and community organizations created Our Money, Our Solutions (OMOS), an alternative plan listing needed improvements that cost less than the MOC’s original $23 million budget.

Some OMOS priorities have come to pass, such as weekend service on the 93 bus line and Second Avenue/Irvine Street sidewalk repairs in progress. But critical items—such as traffic-calming measures on Hazelwood Avenue and lower Greenfield Avenue and those discussed at the February 17 meeting with Mayor Gainey—remain unaddressed. Why is bike trail infrastructure being prioritized over needs like these? City parks already have a dedicated source of revenue from taxpayers, while neglect has destroyed existing infrastructure in these communities over decades.

“We said at the February 17 meeting that we are looking to put in a request for money for repairs and improvements for Burgwin [Recreation Building],” Councilman O’Connor said, explaining those funds would not come from the MOC budget.  

He added this is the first year City Council will have park tax funds to work with, and they have not yet finalized the process for distributing them.

Meanwhile, explorations into the mysteries of MOC funding continue. In a May 27 email responding to inquiries, City Controller Michael Lamb said his office will soon release their performance audit of several city departments. The audit included a review of the MOC that helped inform Mayor Gainey’s decision to end the project.

End of MOC Shuttle Program Begins New Community Conversation with Mayor Gainey

Mayor Ed Gainey and District 5 City Councilman Corey O'Connor at Feb. 17 MOC meeting

On February 17, Hazelwood residents and others gathered at Propel Hazelwood to discuss rapidly evolving developments in the Mon-Oakland Connector (MOC) project. The day before, Mayor Gainey’s office announced an end to the controversial shuttle road that was the essence of the MOC.

The meeting, hosted by the Greater Hazelwood Community Collaborative (GHCC), brought a wide range of human interactions and emotions: sometimes heated, sometimes funny, occasionally joyful. Some attendees remarked that it was their first in-person meeting in months or years. The auditorium burst into thunderous applause several times—including after Propel Hazelwood students performed “Lift Every Voice and Sing,” and especially when Mayor Gainey said, “The Mon-Oakland shuttle project will not go forward.”

Moving forward together

Mayor Gainey’s announcement marks a huge turning point in MOC-affected communities’ battle to reclaim their tax dollars and voice in their future. It is an opportunity to repair public trust that was shattered by 6.5 years of pushing the MOC over multi-community opposition.

The battle is far from over. Already the Pittsburgh Post-Gazette is writing op-eds attempting to resuscitate the weak case for MOC shuttles in the future. And the needs of existing 15207 residents still lack attention and funding the now-defunct MOC continues to enjoy. As the new Gainey administration works with our communities on building a new way forward, focus should be redirected to:

  • Critical needs in Hazelwood. Though Councilman Corey O’Connor moved some funds from the MOC, it still has about $7 million. Early reports indicate most of the MOC’s original $23 million budget will be restored for a new bike trail and improvements to Schenley Park and the Hazelwood Greenway (now also designated as a city park). Parks and infrastructure are both important, and should not be pitted against each other. Even the loveliest bike trail should not be prioritized over basic necessities for Hazelwood like safe street crossings, sidewalks, and facilities for after-school programs. City parks already have a dedicated source of revenue from taxpayers, while neglect has destroyed Hazelwood’s infrastructure over decades.

  • A stronger stormwater plan in The Run and Schenley Park—unhampered by the MOC. The Pittsburgh Water and Sewer Authority’s (PWSA’s) $42.65 million stormwater project, touted as a way to fix severe flooding in The Run, came after and was designed around the MOC shuttle road. For years, residents were told these were two separate projects and that PWSA’s efforts could easily move forward regardless of the MOC’s fate. That message has changed recently, but Run residents, who have been awaiting flood relief for decades, value effectiveness over speed. For years they have challenged PWSA to provide a stormwater model that does not include the MOC. Instead, PWSA compared the MOC-centric design against doing nothing. The Run has an opportunity to finally see how much better PWSA can address flooding now that accommodating a shuttle road has been dropped from their project requirements.

  • Transportation solutions that improve rather than undermine public options. The Our Money, Our Solutions (OMOS) plan, created by MOC-affected communities with help from Pittsburghers for Public Transit, contains many improvements that would serve residents and the Hazelwood Green development. Some of those improvements, such as weekend service for the 93 bus line and Irvine Street sidewalk repairs, have already been secured. Others, like extending the 75 bus line into Hazelwood, are under consideration. If we don’t adopt OMOS wholesale, we can at least revisit and borrow heavily from it.

Our new plan needs a new name to reflect new priorities

We all deserve a fresh start to distance ourselves from the dishonesty and corruption that plagued the MOC from the start. The MOC quickly became a “magic bag” of components and costs that shifted according to justifications needed for it at any given time. Only the shuttle road has remained consistent. Now that the road has been removed, this project is no longer the MOC. Any work in Schenley and Hazelwood parks must have a clear focus and leave non-transparency behind.

You can view a livestream of the meeting provided by Center of Life.

Photo courtesy of Juliet Martinez for The Homepage

Irvine Sidewalk Repairs Receive Funding

Construction Projected for Summer 2022

Long-needed sidewalk construction on Irvine Street between Hazelwood and Greenfield avenues got more attention recently when updates to the project’s Engage PGH webpage raised questions about funding.

Although the fact sheet linked from the webpage stated “this project is only funded for design. DOMI [Pittsburgh’s Department of Mobility and Transportation] is investigating potential sources for construction funds…,” construction is funded and slated to begin in June.

DOMI’s chief engineer Eric Setzler said the project received a grant of $120,000 from the Pennsylvania Department of Community and Economic Development, plus $1 million in funding from the $335 million Pittsburgh received as part of the American Rescue Plan (ARP).

Mr. Setzler reported that the Irvine Street project mainly consists of sidewalk and curb replacements with “updated ADA [Americans with Disabilities Act-compliant] ramps at the intersections.”

“We would like to get as much curb reveal as possible,” he said, referring to the height of a curb that helps provide separation from the road. As layers of asphalt are added to a road over time, its level rises closer to the adjacent sidewalk. Other Irvine Street improvements include adjusting drainage from the sidewalks and adding a small retaining wall to “hold the slope back”—especially near the Greenfield Avenue end of Irvine Street. The area currently has rock-filled wire cages called gabion baskets.

Mr. Setzler added that the project is “on a good track,” with design scheduled to wrap up by late January.

Run resident Barb Warwick noticed the outdated fact sheet and commented on the page, along with several other community members, calling for construction funds to be taken from the budget of the unpopular Mon-Oakland Connector (MOC).

“$12 million is a lot of money and it’s just sitting there in DOMI’s coffers,” Ms. Warwick said, referring to the estimated MOC budget. “Now that everyone is finally acknowledging how misguided DOMI’s plan to build a shuttle road through Schenley Park really was, we can start using that money for mobility improvements the people of Pittsburgh actually need.”

Regarding the MOC budget, Mr. Setzler said, “I am seeing about $8 million [of City funds], not counting anything from PWSA [Pittsburgh Water and Sewer Authority].” He mentioned the $4 million difference had been redirected in the 2021 budget through an amendment introduced by District 5 Councilman Corey O’Connor. PWSA has a budget of more than $42 million to complete a stormwater project on the same land as the MOC.

The MOC, slated to be put on hold by incoming Pittsburgh mayor Ed Gainey, proposed connecting Oakland university campuses and the Hazelwood Green development through the park’s Junction Hollow section and two adjacent neighborhoods—The Run and Panther Hollow. Affected communities including The Run, Panther Hollow, Greenfield, South Oakland, and Hazelwood created their own plan for how MOC funds should be spent instead: Our Money, Our Solutions (OMOS).

The ARP funding arises from controversy as well. When it was announced in July 2021, Mayor Bill Peduto drew criticism from constituents who said he needlessly rushed to set a major spending agenda that prioritized infrastructure above mitigating COVID-19-related harms, such as evictions.

Anna Tang, a community organizer with BikePGH, received an email alert about the page update on Dec. 3; she forwarded it to her contacts in the Greenfield/Hazelwood area. “It’s my job to let the public know about this stuff,” Ms. Tang said, speaking as a citizen familiar with City websites rather than as a representative of BikePGH.

“This is an important corridor for all modes of transportation,” Ms. Tang remarked, “and it seems like the most vulnerable users are almost always last to get the infrastructure attention they need. [The sidewalk repairs] couldn’t come soon enough.”

“To be 100% honest, there’s not a whole lot of things to provide feedback on,” Mr. Setzler said of the project’s Engage PGH webpage. “But we still want to put it out there and let people see it.”

Although other city departments have been sharing their projects on Engage PGH for longer, “DOMI is catching up,” Mr. Setzler added. “Going forward [Engage PGH] will be our main source for sharing project information. In general, projects will still have outreach to community groups and public meetings”—virtual or in person.

As of Dec. 14, the project page had an updated fact sheet and a new “virtual public plans display.” The display features maps and a schedule that projects construction will take seven months. In addition, a new feedback form was placed on the page above the existing 140-character comment field. You can also create an Egage PGH account to receive email alerts about upcoming projects in areas you choose from a list.